Vanzant Court Sewer Replacement and Road Reconstruction

Share on Facebook Share on Twitter Share on Linkedin Email this link


This project will see the replacement and lowering of the sanitary sewer, replacement and separation of residential sanitary sewer lateral connections, road reconstruction, and curb/boulevard restorations.


Progress Update and Schedule

The project is intended to commence during the week of August 8th and is anticipated to be substantially complete within 10 weeks.

Generally, the sequence of work includes:

  • Contractor mobilization and preparation
  • Removal and replacement of sanitary sewer infrastructure
  • Road cuts and material disposal
  • Reconstruction of road base
  • Concrete work
  • Base Asphalt
  • Boulevard restoration and driveway repairs
  • Top Asphalt
  • Final restoration


Weekly Updates

August 16, 2021

  • Work commenced on August 12, 2021 with site layout, utility markings, equipment staging, and construction signage.
  • Pre-construction inspections have been completed.
  • Removal of the existing asphalt surface is complete in preparation for sewer excavation.
  • Replacement and lowering of the sewer pipeline is expected to continue for the next 2 to 3 weeks. Work will begin at the Stouffer intersection and move towards the cul-de-sac.
  • Once the main sewer pipeline is completed, individual lateral connections will be completed beginning in the cul-de-sac and moving towards the Stouffer intersection. This is expected to last 1 to 2 weeks.

August 23, 2021

  • Work on the main sewer pipeline is underway with a few challenges that have slowed production this past week.
  • More groundwater than expected has been encountered in the excavation which requires set-up of additional pumping equipment
  • Residential Garbage/Recycling and Green Bin collection will continue on the regular pick-up schedule, however pick-up times will be adjusted to 7am. Please ensure all materials are placed as close to their usual position by 7am.

September 13, 2021

  • Work continues with the installation and commissioning of a dewatering system to ensure future excavations remain dry.
  • Excavation and sewer work is anticipated to resume on Sept. 16th and continue for approximately 3 weeks
  • Project completion remains on schedule, however any further delay may impact the completion date

October 01, 2021

  • The dewatering system has been effective and sewer excavation has recommenced
  • Sewer work is anticipated to continue for the next 2 weeks, weather depending
  • Progress of the work is meeting expectations however the project team is exploring options to accelerate the work


COVID-19 Information

Policies and procedures are in place to ensure that the work meets all public health directives and best practices for construction.



This project will see the replacement and lowering of the sanitary sewer, replacement and separation of residential sanitary sewer lateral connections, road reconstruction, and curb/boulevard restorations.


Progress Update and Schedule

The project is intended to commence during the week of August 8th and is anticipated to be substantially complete within 10 weeks.

Generally, the sequence of work includes:

  • Contractor mobilization and preparation
  • Removal and replacement of sanitary sewer infrastructure
  • Road cuts and material disposal
  • Reconstruction of road base
  • Concrete work
  • Base Asphalt
  • Boulevard restoration and driveway repairs
  • Top Asphalt
  • Final restoration


Weekly Updates

August 16, 2021

  • Work commenced on August 12, 2021 with site layout, utility markings, equipment staging, and construction signage.
  • Pre-construction inspections have been completed.
  • Removal of the existing asphalt surface is complete in preparation for sewer excavation.
  • Replacement and lowering of the sewer pipeline is expected to continue for the next 2 to 3 weeks. Work will begin at the Stouffer intersection and move towards the cul-de-sac.
  • Once the main sewer pipeline is completed, individual lateral connections will be completed beginning in the cul-de-sac and moving towards the Stouffer intersection. This is expected to last 1 to 2 weeks.

August 23, 2021

  • Work on the main sewer pipeline is underway with a few challenges that have slowed production this past week.
  • More groundwater than expected has been encountered in the excavation which requires set-up of additional pumping equipment
  • Residential Garbage/Recycling and Green Bin collection will continue on the regular pick-up schedule, however pick-up times will be adjusted to 7am. Please ensure all materials are placed as close to their usual position by 7am.

September 13, 2021

  • Work continues with the installation and commissioning of a dewatering system to ensure future excavations remain dry.
  • Excavation and sewer work is anticipated to resume on Sept. 16th and continue for approximately 3 weeks
  • Project completion remains on schedule, however any further delay may impact the completion date

October 01, 2021

  • The dewatering system has been effective and sewer excavation has recommenced
  • Sewer work is anticipated to continue for the next 2 weeks, weather depending
  • Progress of the work is meeting expectations however the project team is exploring options to accelerate the work


COVID-19 Information

Policies and procedures are in place to ensure that the work meets all public health directives and best practices for construction.