Asphalt Paving and Resurfacing - 2019

Share on Facebook Share on Twitter Share on Linkedin Email this link


What is the 2019 Asphalt Paving and Resurfacing project?

The Public Works - Capital Projects division undertakes an annual program of roadway paving and resurfacing aimed at renewing and extending the life of the Town’s road infrastructure. Candidate roadways are identified through various condition assessments, maintenance histories, resident complaints, and future development considerations. The 2019 program incorporates approximately 10km of roadway repaving and resurfacing.

Road
From
To
Bethesda Road
Kennedy Road
McCowan Road
Vandorf Sideroad
Woodbine Avenue
Kennedy Road
St. John’s Sideroad
Warden Avenue
Kennedy Road
Raeview Drive
Hilltop Trail
West Limit
Service Road
Palmwood Gate
East Limit
Aintree Drive
10th Line
Cam Fella Boulevard
Cam Fella Boulevard
Aintree Drive
North Cul-De-Sac Limit
Blair Road
Stouffer Street
Dorman Drive
Thicketwood Boulevard
Lori Avenue
Booth Drive


Bethesda Road from Kennedy Road to McCowan Road.

Existing asphalt surface will be pulverized, regraded, compacted. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Vandorf Sideroad from Woodbine Avenue to Kennedy Road.

Existing asphalt surface will be pulverized, regraded, compacted. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

St. John’s Sideroad from Warden Avenue to Kennedy Road.

Existing asphalt surface will be pulverized, regraded, compacted. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Raeview Drive from Hilltop Trail to the westerly road limits.

Existing asphalt surface will be pulverized, regraded, compacted. A new asphalt surface will then be placed. Driveways will be restored, granular shoulders placed and compacted, and new line painting will be completed.

Service Road from Palmwood Gate to the easterly road limit.

Existing asphalt surface will be pulverized, regraded, compacted. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Aintree Drive from 10th Line to approximately #517 Aintree Drive.

Existing asphalt surface will be pulverized, regraded, compacted. Concrete curbs will be removed and replaced. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Approximately #517 Aintree Drive East to Cam Fella Boulevard.

Removal of existing asphalt, excavation and disposal of existing road base material. Installation of a geosynthetic stabilization mat. Removal and replacement of existing curb, gutter, and subdrains as well as catchbasin relocation. Installation and compaction of new road base material. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Cam Fella Boulevard from Aintree Drive to the North Cul-De-Sac limits.

Existing asphalt surface will be pulverized, regraded, compacted. Concrete curbs will be removed and replaced. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Blair Road from Stouffer Street to Dorman Drive.

Existing asphalt surface will be pulverized, regraded, compacted. Sections of concrete curb and gutter will be replaced as necessary. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Thicketwood Boulevard from Lori Avenue to Booth Drive.

Existing asphalt surface will be pulverized, regraded, compacted. Sections of concrete curb and gutter will be replaced as necessary. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.


Progress Update - April 30, 2020

Remaining work is expected to begin on the week of May 04, 2020 for an approximate duration of 3 weeks.

Vandorf Sideroad : Complete
St John’s Sideroad : Complete
Bethesda Road : Complete
Service Road : Complete
Blair Road : Complete
Thicketwood Blvd : Complete
Aintree Drive : Top asphalt beginning the week of May 04, 2020
Cam Fella Blvd : Top asphalt beginning the week of May 04, 2020
Raeview Drive : Asphalt repairs, top asphalt, driveway adjustments, and granular shouldering beginning the week of May 04, 2020

Covid-19: Policies and procedures are in place to ensure that the work meets all public health directives and best practices for construction.



What is the 2019 Asphalt Paving and Resurfacing project?

The Public Works - Capital Projects division undertakes an annual program of roadway paving and resurfacing aimed at renewing and extending the life of the Town’s road infrastructure. Candidate roadways are identified through various condition assessments, maintenance histories, resident complaints, and future development considerations. The 2019 program incorporates approximately 10km of roadway repaving and resurfacing.

Road
From
To
Bethesda Road
Kennedy Road
McCowan Road
Vandorf Sideroad
Woodbine Avenue
Kennedy Road
St. John’s Sideroad
Warden Avenue
Kennedy Road
Raeview Drive
Hilltop Trail
West Limit
Service Road
Palmwood Gate
East Limit
Aintree Drive
10th Line
Cam Fella Boulevard
Cam Fella Boulevard
Aintree Drive
North Cul-De-Sac Limit
Blair Road
Stouffer Street
Dorman Drive
Thicketwood Boulevard
Lori Avenue
Booth Drive


Bethesda Road from Kennedy Road to McCowan Road.

Existing asphalt surface will be pulverized, regraded, compacted. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Vandorf Sideroad from Woodbine Avenue to Kennedy Road.

Existing asphalt surface will be pulverized, regraded, compacted. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

St. John’s Sideroad from Warden Avenue to Kennedy Road.

Existing asphalt surface will be pulverized, regraded, compacted. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Raeview Drive from Hilltop Trail to the westerly road limits.

Existing asphalt surface will be pulverized, regraded, compacted. A new asphalt surface will then be placed. Driveways will be restored, granular shoulders placed and compacted, and new line painting will be completed.

Service Road from Palmwood Gate to the easterly road limit.

Existing asphalt surface will be pulverized, regraded, compacted. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Aintree Drive from 10th Line to approximately #517 Aintree Drive.

Existing asphalt surface will be pulverized, regraded, compacted. Concrete curbs will be removed and replaced. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Approximately #517 Aintree Drive East to Cam Fella Boulevard.

Removal of existing asphalt, excavation and disposal of existing road base material. Installation of a geosynthetic stabilization mat. Removal and replacement of existing curb, gutter, and subdrains as well as catchbasin relocation. Installation and compaction of new road base material. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Cam Fella Boulevard from Aintree Drive to the North Cul-De-Sac limits.

Existing asphalt surface will be pulverized, regraded, compacted. Concrete curbs will be removed and replaced. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Blair Road from Stouffer Street to Dorman Drive.

Existing asphalt surface will be pulverized, regraded, compacted. Sections of concrete curb and gutter will be replaced as necessary. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.

Thicketwood Boulevard from Lori Avenue to Booth Drive.

Existing asphalt surface will be pulverized, regraded, compacted. Sections of concrete curb and gutter will be replaced as necessary. A new asphalt surface will then be placed. Driveways and shoulders will be restored, and new line painting will be completed.


Progress Update - April 30, 2020

Remaining work is expected to begin on the week of May 04, 2020 for an approximate duration of 3 weeks.

Vandorf Sideroad : Complete
St John’s Sideroad : Complete
Bethesda Road : Complete
Service Road : Complete
Blair Road : Complete
Thicketwood Blvd : Complete
Aintree Drive : Top asphalt beginning the week of May 04, 2020
Cam Fella Blvd : Top asphalt beginning the week of May 04, 2020
Raeview Drive : Asphalt repairs, top asphalt, driveway adjustments, and granular shouldering beginning the week of May 04, 2020

Covid-19: Policies and procedures are in place to ensure that the work meets all public health directives and best practices for construction.