Ballantrae Sidewalk Construction

Share Ballantrae Sidewalk Construction on Facebook Share Ballantrae Sidewalk Construction on Twitter Share Ballantrae Sidewalk Construction on Linkedin Email Ballantrae Sidewalk Construction link
A person smoothing concrete for a new sidewalk

Phase 1 – Aurora Road (north side), from McMullen Drive to Ballantrae Gates Plaza

The Town has awarded the tender for construction of a sidewalk along Aurora Road (north side), from McMullen Drive to Ballantrae Gates Plaza to Quality Property Services (QPS). The work includes:

  • Clearing and grubbing along the sidewalk alignment;
  • Installation of 2.0m wide asphalt sidewalk;
  • Line painting and tactile plate installation; and
  • Drainage culvert and grading works.

Work will begin once weather conditions allow.

WSP Canada Inc. has been retained to provide full time site inspection services during construction.

Any planned disruptions to driveway access or Town services will be communicated in advance. Please label your trash and recycling containers as the Contractor may be required to move these containers once work is underway. The Town is not responsible for damage or loss to privately-owned appurtenances located within the public road right-of-way. Please ensure that any such appurtenances are removed prior to construction.


What’s Next?

(Schedule subject to change based on weather conditions)

  • May 21: Mobilization, preparations, and layout work begins.
  • Week of May 26: Traffic control measures and earthworks.
  • Week of June 2: Culvert installation and concrete works.
  • Week of June 9: Concrete works and asphalt installation.
  • Week of June 16: Pavement markings and inspections.


Phase 2 – Highway 48 (east side), from Ballantrae Gates Plaza to Ballantrae Common

The Town has retained the services of WSP Canada Inc. to complete the investigation and design for this portion of the sidewalk works.

Phase 1 – Aurora Road (north side), from McMullen Drive to Ballantrae Gates Plaza

The Town has awarded the tender for construction of a sidewalk along Aurora Road (north side), from McMullen Drive to Ballantrae Gates Plaza to Quality Property Services (QPS). The work includes:

  • Clearing and grubbing along the sidewalk alignment;
  • Installation of 2.0m wide asphalt sidewalk;
  • Line painting and tactile plate installation; and
  • Drainage culvert and grading works.

Work will begin once weather conditions allow.

WSP Canada Inc. has been retained to provide full time site inspection services during construction.

Any planned disruptions to driveway access or Town services will be communicated in advance. Please label your trash and recycling containers as the Contractor may be required to move these containers once work is underway. The Town is not responsible for damage or loss to privately-owned appurtenances located within the public road right-of-way. Please ensure that any such appurtenances are removed prior to construction.


What’s Next?

(Schedule subject to change based on weather conditions)

  • May 21: Mobilization, preparations, and layout work begins.
  • Week of May 26: Traffic control measures and earthworks.
  • Week of June 2: Culvert installation and concrete works.
  • Week of June 9: Concrete works and asphalt installation.
  • Week of June 16: Pavement markings and inspections.


Phase 2 – Highway 48 (east side), from Ballantrae Gates Plaza to Ballantrae Common

The Town has retained the services of WSP Canada Inc. to complete the investigation and design for this portion of the sidewalk works.